| 1 |
Barabanki [NIMSME] |
1 |
Construction Completed. |
Construction completed.Connection for electric supply ,The estimate charge of Rs 2,13,585/-is paid to electrycity Board.Machine for lab of CFC is stalled and Quotation open for CFC . |
2 |
1 Dye house is upgraded & Functional.
Another one Dye houses to be upgraded. |
In the functional upgraded dye house, first time Fast coloring is achieved in the cluster
Compound Wall constuction is going on for both the dye house. Dyeing vessels purchase by the compony. |
| 2 |
Bargarh [BOYANIKA] |
1 |
Functional |
3 Components of CFC are functional. i) Quality Testing Laboratory (QTL) - installed with modern testing equipments ii) Cluster Information Centre (CIC) - Well equipped with books and periodicals in the library. Regularly used by the stakeholders. iii) Dyestuff & Chemical Bank - 2062 kgs of dyes /chemicals purchased from NHDC out of which 727 kgs used by the stakeholders |
1 |
Functional |
Water Softening Plant installed. Vegetable Dyeing Unit set up. Average 100 kgs. Of yarns per day are dyed in the dyehouse. |
| 3 |
Bhagalpur - [ASSED] |
1 |
Functional |
CFC is running successfully. |
1 |
Functional |
Till the date more then 5200 kgs of yarn dyed generating revenue of Rs.7.23 lakhs. |
| 4 |
Bijoynagar [SIRD] |
1 |
Functional |
##CFC: The CFC is presently used for sample development, product development & Training. Moreover CFC is also used for making the products as per the order being received by the consortium. At present there are 12 nos. looms in working condition. 12 nos. jacquard machine, 2 nos. warping drums, 2 nos. Muga reeling & twisting machine, 01 no Re Reeling machine,
1 no. eri spinning machine & 06 nos, Cycle Frame Charkas to assist the weavers at the CFC.
##Quality Control lab and CAD Centre established.
|
1 |
Functional |
Average 30 to 40 Kgs of Eri & Cotton yarn died every month.DH: The dye house is use for training, sample development, product development. There are 01 no hank dyeing machine, 01 no. laboratory dyeing machine, 01 no hydro executor & 01 no electronic weighing balance. More emphasis has been put on the training of natural dye for the beneficiaries of cluster.
|
| 5 |
Bijnore [Textiles Committee] |
1 |
Construction completd |
Construction completd.
[List of equipments and attachments for various componnts of CFC with current market rate has been sent to HQ for approval and inviting tender] |
1 |
Construction icompletd |
[60% paymnt for fourth bill from the machinery supplier cleared.Water pipeline, steam line and lctrical panel connection in progress.Hydro extractor and ETP Receivd. Fourth bill from supplier for 10.99 lacs forwarded. 70% Payment for Water tank.30% advance paid for water tank construction.] |
| 6 |
Burdwan [NHDC] |
1 |
Ready to Work |
Civil work completed. Machineries installed. Sample production already started in loom centre.48 pcs of Tangail sarees produced by using 2 sample looms |
1 |
Functional |
Commercial production started from March 1st, 2011. So far 38 Half Bales i.e., 3450.40 kgs of cotton hank yarn dyed & for which Rs. 74500.00 as dyeing charges collected by the producer company. |
| 7 |
Chanderi / Gwalior [EDI] |
1 |
Functional |
CFC is running successfully. Cluster office also shifted at CFC. MoU signed with the Consortium |
1 |
Functional |
Dye house is running successfully at around 70% capacity. Mou singed with the consortium. |
| 8 |
Chirala [APCO] |
1 |
Functional |
Inaugurated on 3rd November 2009. MoU signed with the consortium. |
1 |
Functional |
Dye house has been inaugurated on 3rd November 2009. ETP Plant established for Dye house.Commercial dyeing started from 1st April 2010. So far 346 bales of 39,030 kgs of yarn was dye and supplied to 1800 weavers and master weavers. |
| 9 |
Gadag [KHDC] |
1 |
Functional |
CFC Functional. Installed 6 Looms at Workshed for development of new samples. A Meeting hall, Raw Material Depot, Display Hall & Office of the CDE established. |
1 |
Functional |
Established Dye house at Gadag with capacity of 200 kgs per day of cotton yarn & 20 kgs of silk yarn. Installed Cabinet Hank Dyeing Machines, Hydro-extractor, Mini Boiler, Generator Silk Hank Dyeing Machine & Drying Yard. The dyeing work is taken up. |
| 10 |
Imphal [IIE] |
1 |
Functional
|
CFC is running under IIE supervision. Production of newly developed design is going on in the premise. |
1 |
Inaugurated in August,09
|
Dyeing unit is operationalising under a master dyer, trained by WSC, Imphal. Daily dyed yarn production is 10-15 kgs per day under IIE supervision. It is identified to transfer the running by the CDCC members. |
| 11 |
Kullu [HPHHDC] |
1 |
Functional |
CFC building renovated. 16 Handloom installed. Regular employment is provided to 16 weavers. Prototypes are developed. 800 weavers benefited through CFC. Production in CFC is 20 lakh |
1 |
Nil |
NO Dye house set up. |
| 12 |
Kurinjipadi [COOPTEX] |
1 |
Activity Dropped |
Dropping of CFC is approved in last Apex Committee meeting |
1 |
Activity Dropped |
Setup of Dye house will NOT be done due to Pollution issue in the state as per decision taken by Director of Handloom & Textile, Chennai, Tamilnadu.
|
| 13 |
Madhavaram[APCO] |
1 |
Functional |
CFC is not functional due to internal issue among the Consortium members |
1 |
Functional |
Dye house is running successfully. So far 10 bales of 908 kgs of yarn was dyed and supplied to 27 master weavers . |
| 14 |
Mubarakpur [NIMSME] |
1 |
Construction Completed. |
Construction completed. |
2 |
1st Dye house Functional
2nd Dye house to be upgraded. |
1st Dye House functional - Daily about 60 Kg yard is dyed.
IA is waiting for 20% contribution from the beneficiary. |
| 15 |
Shantipur (Nadia) [Textiles Committee] |
1 |
The land of the CFC was provided by Shantipur Lifeline HL Weavers Welfare Society (SHG Federation).CFC sanctioned in the year 2009-10 |
Construction up to 1st floor is completed. Construction is On Progres * Revised Tender documents placed by Certified Engineer & Sent to HQ for approval |
1 |
Land Identified. |
Work order has been placed for Dyeing machines for Dye House in Nov 11. M/s Tangail Tantujibi Unnayan Samabay Samity Limited of Belgoria has provided 30% contribution for for upgradation of modern dye house.
[Earlier M/s Shantipur Kutirpara Society Limited show interest but later opted out, since plot has not vacated & 20% share not paid by the society. ] |
| 16 |
Sonepur [EDI] |
1 |
Functional |
Functional |
2 |
Functional |
Functional.
Dye House of Sagarpali & Birmaharajpur are operational. |
| 17 |
Tiruvannamalai [COOPTEX] |
1 |
Land Identified. |
Land has been identified at Arni. |
1 |
Separate proposal will be submitted. |
Setup of Dye house will NOT be done due to Pollution issue in the state as per decision taken by Director of Handloom & Textile, Chennai, Tamilnadu. |
| 18 |
Trichy [Textiles Committee] |
1 |
Land Identified.
|
Consortium finalized land and made full payment for CFC and the registration is made in the name of the Managing Director. (Land is situated in residential area by the revenue dept. yet to issue NOC)
|
1 |
Land Identified.
|
NOC received from TAMILNADU POLLUTION CONTROL BOARD FOR AWARDING NOC. I/A has received concent letter from TNPCB on 22nd sept. 2011 fro establishment of Dye House.
|
| 19 |
Trivandrum [HANVEEV] |
1 |
Construction Completed. |
Weaving work shop loom errection ,Q C Lab equipment errection is in progress. |
1 |
Partially functional using Dying tanks.
machineries installed |
Per day about 4.5 kg yarn is dyed. Boiler installed.
Dye house will be fully functional by the end of February,2010. |
| 20 |
Varanasi [EDI] |
1 |
Functional |
Construction work completed, well furnished & all machine & equipments installed. (Functional) |
7 |
6 Upgraded & Functional
(Lohta, Ramnagar & Kotwa)
1 new built -Functional.
|
MoU done with the Dye house owner and the dyeing charges have been fixed. Per day on an average (40 to 50) Kg yarn is being done (Dyed) in all the up-graded and newly constructed Dye House on regular basis.
Up-Gradation of Garib Nawaj Dye house is on process. |
| |
TOTAL |
20 |
|
|
29 |
|
|
| |
|
|
SUMMARY - Nineteen CFCs are Functional. |
|