Progress Report 2008 - 2009 and Action Plan 2009 - 2010
Name of the Cluster: Bijnor          
IMPLEMENTING AGENCY: Textiles Committee
PROGRESS REPORT [2008-09] & ACTION PLAN [2009-10]
2008-09 2009-10
Amount Sanctined : Rs 53.70 Amount Proposed : Rs 33.00 lakhs
Amount Utilized : Rs 17.80
% of Utilization :  
2008-09
[Updated till 31st July,2009]
2009-10
[Proposed]
Sl. No. Physical Activity               Physical
Target [Frquency / No:]
Financial Target
[Rs. In lakhs]
Physical
Achievement
[2008-09]
Financial Achievement [2008-09]
[Rs in lakhs] 
Remarks  Physical
Target [Frquency / No:]
Financial Target
[Rs. In lakhs]
  1 2 3 4 5 6 7 8
A Formation & Strengthening of Institutions        
1 Formation of SHGs 20 0.60 _ _ 40 SHGs formed.    
2 Formation and strengthening of consortium 2 1.50 _ _      
B Market Linkages              
3 Domestic buyer seller meet
3 4.00 6 7.87 Hasthkala expo Bangalore, Brand India Fair Gujarat,EDI  Cluster ExpoBangalore,EDI  Cluster ExpoAhmedabad,Hasthkala expo Ahmedabad,Texstyles Fair Delhi , Dilli Haat Exhibitions.
Activity Continued.
6 8.00
4 Exhibition cum sale outside cluster in metro cities cum sale within cluster
6 8.00
5 Publicity 4 1.00 3 0.85 Product catalogue, CD, Nitche product tag
Activity Continued.
1 0.90
C Financial Linkages 2 0.50 2 0.25 Two rounds of meetings with Nabard and PNB Officials.
   
                 
D Design & Product Development        
6 Designer Salary   3.60   3.90 Designer salary. Activity Continued.   3.60
7 Product development   3.50   1.30 Development of four new designs  by Designer for further converting into final products. Four Coordinate sets of Homefurnishing items developed for displaying in the Texstyles Fair-2009 at Pragati Maidan .
stoles and fabrics developed for MRP exports, Noida. String curtains in new colours developed for Home and we.
Activity Continued.
  1.00
E TRAINING & Capacity building              
8 Skill upgradation,Dobby design training, Handblock printing  9 4.50 2 0.85 Two trainings in Handblock printing completed. Five more trainings to be conducted.
[Sanction subject to submission of DPR to the O/o DC - HL] 
8 4.00
9 Dyers workshop 1 0.50          
F Infrastructure Creation.              
G Accessories Supply              
10 Accessories supply         Activity Continued. Reeds & Healds 300 5.00
H Yarn Supply Corpus               
I Monitoring              
11 CDCC meeting 4 0.50 1 0.13      
12 Engagement of  professional/ technical service provider for the association consortium
1 1.00 1 0.55 Cluster technical assistant salary 1 1.00
  NEW ACTIVITIES SANCTIONED FOR 2008-09            
13 Technology up gradation ( Five wheel Take-up motion) 50 3.00 20 1.10 Fivewheel take up motion for 20 looms ordered    
14 Interactive meeting of stakeholders  2 0.50 _ _      
15 Establishment of Additional Dye house 1 20.00 _ _      
16 HANDLOOM MARK Registration   1.00 _ 1.00 Inspection in progress for 5o societies
Activity Continued.
25 0.50
  GRAND TOTAL [In Rs Lakhs] 53.70 17.80      
J         New Activities Proposed for the year 2009-10    
17           Motorised Warping M/c with creel and Bobbins
[PPP Mode 80:20] 
10 2.00
18     Difference in construction cost of CFC and Dye House
(Subject to submission of DPR)
  6.50
19           Video film 1 0.50
  GRAND TOTAL    53.70   17.80 GRAND TOTAL    33.00