Progress Report 2008 - 2009 and Action Plan 2009 - 2010
Name of the Cluster:   Bhagalpur       
IMPLEMENTING AGENCY: ASEED
PROGRESS REPORT [2008-09] & ACTION PLAN [2009-10]
2008-09 2009-10
Amount Sanctioned: Rs. 63.60 Amount Proposed : Rs. 23.65  lakhs
Amount Utilized : Rs 30.37
% of Utilization :  47.75
2008-09
[Updated till 31st July,2009]
2009-10
[Proposed]
Sl. No. Physical Activity               Physical
Target [Frquency / No:]
Physical
Achievement
[2008-09]
Financial Target
[Rs. In lakhs]
Financial Achievement [2008-09]
[Rs in lakhs] 
Remarks  Physical
Target [Frquency / No:]
Financial Target
[Rs. In lakhs]
1 2 3 4 5 6 7 8 9
A Formation & Strengthening of Institutions            
1 Formation of SHG 50 46 1.50 1.38 46 SHG formed & bank account oppened 20 0.60
2 Formation & strengthening of Consortium. 1 3 1.00 0.25 3 Consortium formed & registered under society Act 1860(21) 1 0.75
3 Stake Holder Workshop 2 1 0.50 0.22 One workshop organised 105 wevers, 16 local traders/Exporters & 12 officials participated 1 0.25
4 GI registration of Bhagalpur product 1 1 1.50 0.00 Application has been filed to Registrar Chennai with technical support of Textiles committee & financial support of UNCTAD India. -- --
B Market Linkages              
6 Exhibition/BSM 10 19 17.00 6.26 Participated in all silk fab, Handloom expo, cluster expo, Barodra expo,consumer fair, Bhagalpur,Delhi,Kolkata,Banglore,Chandigarh BSM, total retail sales generated of Rs, 5 7.50
7 Handloom Mark Registration 5 37 1.00 0.90 25 SHG & 12 individuals registered 25 0.60
C Financial Linkages              
8 Bankers Meeting 6 4 0.60 0.22 4 meetings with 22 bankers has been conducted 13 new SHG got revolving fund of Rs. 25000/- each, bankers are not cooperating due to NPA of out standing loans by weavers. -- --
D Design & Product Development              
9 Designers Engagement 1 1 3.60 3.60 22 new designs of Sari, Scarves, Stoles & Bed sheet has been introduced. 1 3.60
10 New product Development 1 1 4.00 2.06 129 samples of 29 new Designs has been prepared & product catalogue prepared. 1 2.00
E TRAINING & Capacity building              
11 Training of Cooperative/Federation management 4 3 1.00 0.70 3 Training Programs of 2days has been organised with the help of IRDPC & DRDA, 339 weavers participated 2 0.50
12 Exposure Visit of weavers 2 1 1.50 0.48 Exposure visit of Varanasi Handloom Cluster for 21 weavers & Technical coordinator has been done to learn more about Jaquard weaving on Sari & work with Take-Up motion. 1 0.75
13 Skill development training on Jacquard weaving & printing 2 0 1.00 0.00 Selection of participants has been done with the help of WSC & training scheduled from 16th August. -- --
F Infrastructure Creation.              
14 Boilor for improved Dye 1 1 5.50 3.94 250 kg capacity IBR Boilor has been installed & functioning after certification by Chief Inspector of Boilor & factory Govt. of Bihar only 75% payment has been released to supplier final payment will be released after smonth and successful operation as per term & condition. -- --
15 Jigger for fabric dye 1 1 2.50 1.86 Machinery is under installation, only 75% has been released to supplier. -- --
16 Calender for finishing of fabrics 1 1 2.00 1.59 Machinery is under installation, only 75% has been released to supplier. -- --
17 Screen & handblock printing unit 1 0 3.00 0.00 process of tender has been initiated. -- --
18 Yarn reeling unit 1 0 3.00 0.00 process of tender has been initiated. -- --
19 Tailoring& Embroidery training cum production unit 1 0 5.00 0.00 process of tender has been initiated. -- --
20 Kundi for finishing of product 2 0 0.50 0.00 Quotation called from local supplier -- --
G Accessories Supply              
  5 Wheel Take-up motion 500 500 7.50 6.87 Machinery is under installation, only 90% has been released to supplier. -- --
H Yarn Supply Corpus          Rotation of yarn supply - 5.00
I Monitoring              
21 CDCC Meeting 4 1 0.40 0.05 One meeting conducted by DM another meeting not scheduled. 2 0.10
  GRAND TOTAL     63.60 30.37   -- --
J New Activities Proposed for the year 2009-10          
22 Services of Technical Service Provider To solve day to day problems of weavers during development of new designs & products 1 1.20
23 Training on Manegerial/Technical skill for technical staff for the effective & sustainable operation of CFC & Dye house Essential for effective & hesitation free operation iof CFC & dye house 2 0.80
  GRAND TOTAL [In Rs Lakhs]   23.65